Campus Under Construction

Number 2 - October 2010 - Year 1

 

Decisions Masterplan

On 7 October, a ringing ‘yes’ sounded from Erasmus Universiteit Rotterdam’s Executive Board to phase 1 of the Masterplan. This means a ‘yes’ to projects such as the Student Pavilion, the semi-underground car park, the Erasmus Plaza above the car park, and green space.
Read more>>
Kees Lansbergen, director Erasmus Facility Services

Please register here for newsletter Campus under Construction

 

Architects' pitch Student Pavilion

By 2013, Erasmus University Rotterdam aims to have realized a Student Pavilion that is to become the figurehead of Woudestein campus. For the design of this architectural eyecatcher, 37 architects’ firms have sent in a proposal for design via European tender.  Read more>>

'A shiny new Etude' 

After nearly twelve weeks, the Etude reopened its doors again on 6 September. Apart from noise nuisance, dust and a packed Carrousel, the refurbishment resulted in a bright new Etude. Project manager Cihan Daskapan summed up the process succinctly but meaningfully: ‘high ambitions, snappy project planning, great cooperation’Read more>>

Etude, Erasmus Universiteit Rotterdam

'When seeing these plans, everyone gets a twinkle in their eye'

Bart Straatman, Executive Board, Erasmus University Rotterdam:  ‘Masterplan Woudestein 2028? Great plan! In February last, just after I became a member of the Board, I got my teeth into it. It was finalized by the previous Board, but because we, the new Executive Board, have become so involved in it, it really has become our story. Read more>>

Bart Straatman, Erasmus Universiteit Rotterdam

Trees: planting and felling

2013, Erasmus University’s Centenary year, is drawing near. Preparations for the promising campus developments have begun. The new semi-underground car park and water feature are quite considerable building projects. Differences in level on campus will also be adjusted. Because of this, and because of building logistics, it is necessary to fell a large number of trees. The felling permit was applied for in September. Read more>>

Wednesday 27 October, 2010: information afternoon employees and students

Thanks to the Masterplan, Woudestein’s campus will be transformed into an effervescent world campus over the next few years. The developments will be noticeable in everybody’s working environment. In order to offer first-hand information to one and all, Erasmus Facility Services would like to invite all employees and students to an information meeting on Wednesday 27 October. Read more>>

Alterations to art route

Erasmus University Rotterdam does not only concern itself with academic matters. Plastic arts are important to the university, with which it emphasizes its image. For the approximately fifty statues on campus, Woudestein has even developed its own art route. Because of Woudestein’s approaching housing developments, eight of these outdoor artworks will be (temporarily) relocated or stored. Read more>>

Kunstroute Erasmus Universiteit Rotterdam

Temporary housing lecture halls and shops

Restoration of the C-building, part of a municipal monument, will commence in 2011. Preparations for the restoration have begun with digging works in Institutenlaan. The sequel will be noticeable from early December onwards, when parking lot P1 will be partly occupied by temporary housing for retail and lecture rooms. Read more>>

Erasmus Universiteit Rotterdam

New working environment for ICT

In September, the facelift of the first two floors of the H-building got underway. This will result in a pleasant, modern working environment for SSC ICT. Read more>>

H-gebouw, Erasmus Universiteit Rotterdam

Mail & Logistics in CT-186 until spring 2011 

The department Post & Logistiek (Mail & Logistics) relocated to CT-186 around the end of August. The reason for the move was the refurbishment of the Etude. The department will stay here until spring 2011. Read more>>

 

Would you like to make suggestions about the newsletter, or do you have a question? Please send a mail to campusinontwikkeling@efb.eur.nl.

Yes, I would like to subscibe to this newsletter!

 


Zilveren Kruis Achmea Stair Run

Tuesday 21 May 2013

Testing evacuation system T18

Thursday 16 May 2013

New parking licence? Parking still free until 15 June 2013!

Over the past period, you will have applied for a parking licence.

Entrance building A closed

Friday 26 April 2013