Overall planning until 2013
| Start date | End date |
Preparatory phase: - Plaza - Car park - Campus heart - Reconstruction square C | January 2010 May 2011 January 2012 September 2011
| March 2012 March 2012 October 2012 July 2012
|
Realization phase: - Plaza - Car park - Student Pavilion - U-building - Campus heart - Institutenlaan - Reconstruction square C | October 2012 December 2011 March 2012 January 2012 October 2012 February 2012 October 2011
| March 2013 March 2013 September 2013 September 2013 August 2013 May 2013 March 2013
|