Campus under Construction   Student Pavilion   Planning

Planning Student Pavilion

Building activities September until December 2012

Planning Student Pavilion

The realization phase of the Student Pavilion started in the 2nd quarter of 2012 and will finish in the 3rd quarter of 2013.

 

Start date

End date

Realization phase:
- Construction building shell
- Reaching highest point
- Wind- and waterproof  
- Execution decoration
- Completion
- Putting into use


May 2012
October 2012
December 2012  
April 2013
July 2013
September 2013


March 2013
October 2012
January 2013
July 2013
July 2013
September 2013